14.1 Move through evidence gates

A roadmap is a dependency and risk sequence, not a calendar decorated with milestones. The institution should know what must be learned or demonstrated before the next investment. Durations and budgets are agreed after scope and access are known. The proposed sequence begins with discovery, designs one authoritative journey, pilots it at one office, exercises recovery and expands only after the operating contract works. It preserves an explicit fallback during migration and does not treat data import as proof that business meaning survived.

14.2 Phased delivery

Figure 14.1 · Delivery phases with evidence gates
Delivery phases with evidence gatesProgress is conditional on exit evidence. Durations and budgets are not implied by the diagram; scope and readiness determine the sequence.DiscoverAuthority and definitionsDesignBoundaries and scenariosPilotOne office, one journeyRecoverTimed verified restoreExpandSupport and coverageReviewOperating evidence
Progress is conditional on exit evidence. Durations and budgets are not implied by the diagram; scope and readiness determine the sequence.
PhaseDeliverableExit evidenceAccountable owner
DiscoverCurrent map, evidence and approved definitionsOwners resolve authority and reporting rulesBusiness sponsor
DesignBoundaries, model, contracts and threat reviewNormal, rejected and interrupted journeys explainedArchitecture owner
PilotOne office and one request typePermission, concurrency, retry and reconciliation checksSystem owner
RecoverProtected backup and restoration exerciseApproved recovery objectives demonstratedSystem owner
ExpandControlled rollout and handoverSupport, coverage and freshness demonstratedBusiness and system owners

14.3 Migration and coexistence

Identify which source remains authoritative at every stage. Avoid a transition where two applications can approve the same request independently without a reconciliation rule. Plan reference mapping, data quality treatment, cut-over verification and a controlled way to pause or reverse expansion. Historical records may be incomplete. Record their provenance and limitations rather than manufacturing missing approvals. Decide how legacy evidence remains accessible and who may correct it.

14.4 Acceptance scenarios

ScenarioRequired observation
Lost response after commitRetry retrieves the original result without new work
Stale approvalChanged content requires renewed review
Wrong organizational scopeAction is refused and evidence is retained appropriately
Worker interruptionCommitted decision survives; deferred work resumes
Repeated inputReporting total is not doubled
Late correctionDefined revision policy is applied and explainable
RestoreKnown records, attachments and dependencies reconcile

Acceptance tests require a known initial state and expected result. Keep records of version, environment, scope and observed behaviour. A demonstration on a laptop does not establish production capacity or institutional compliance.

14.5 Handover and closure

Handover includes operating responsibilities, access, runbooks, support expectations, unresolved risks and the next review trigger. The institution accepts the outcome against agreed evidence; completion does not erase open limitations. A delivery phase may be stopped if its assumptions fail. ZAF should make that decision legible before sunk cost turns a weak design into an irreversible commitment.